Sizing AI-Driven Enterprise Engagements Under Uncertainty: A Probabilistic Scope and Pricing Framework for Pre-Sales Architects

Authors

  • Mihir Shah Independent Researcher, USA

DOI:

https://doi.org/10.30871/jaic.v10i5.13744

Keywords:

Pre-Sales Solution Architecture, AI Engagement Estimation, Probabilistic Sizing, Three-Point Estimation, Multi-Phase Pricing, Scope Uncertainty

Abstract

Pre-sales architects who size AI-driven enterprise engagements confront a problem that conventional estimation methods were not built to handle. These engagements combine deterministic components, which established techniques size with reasonable confidence, and probabilistic components, whose effort remains unresolved until implementation begins. Treating every component as deterministic tends to produce chronic underestimation, eroded margins, and delivery teams that inherit commitments they cannot meet. Treating every component as probabilistic surrenders competitive bids to providers willing to offer false certainty. This paper presents a structured framework that sizes each class of component on its own terms and prices the resulting engagement to protect client and provider together. The approach separates stable, fully specifiable work from work that depends on data quality, model behavior, prompt iteration, and evaluation design. Stable components are estimated deterministically. Uncertain components are estimated with three-point ranges aggregated through Monte Carlo simulation rather than summed at their expected values. Pricing follows a multi-phase structure, with discovery, pilot, and scale phases that each carry independent scope, price, and gating criteria, supported by disclosed assumptions that feed contract change management. Operational disciplines of peer review and instrumented post-engagement learning convert individual estimates into an improving organizational capability. A worked illustrative example demonstrates decomposition, ranged sizing, and phased pricing for a customer service assistant engagement. The framework is offered as practitioner guidance grounded in enterprise solutioning experience, with controlled empirical validation identified as future work.

Downloads

Download data is not yet available.

References

[1] S. McConnell, Software Estimation: Demystifying the Black Art. Redmond, WA: Microsoft Press, 2006.

[2] D. D. Galorath and M. W. Evans, Software Sizing, Estimation, and Risk Management: When Performance Is Measured Performance Improves. Boca Raton, FL: Auerbach Publications, 2006.

[3] J. Ryseff and A. Narayanan, "Why AI Projects Fail," RAND Corporation, Rep. PT-A2680-1, 2025. doi: 10.7249/PTA2680-1.

[4] Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th ed. Newtown Square, PA: PMI, 2021.

[5] R. Canesi, L. Gabrielli, and G. Marella, "Probabilistic risk assessment framework for cost overruns predictions in infrastructure projects using randomized simulations," Computer-Aided Civil and Infrastructure Engineering, vol. 40, no. 27, pp. 4774-4796, 2025. doi: 10.1111/mice.70100.

[6] O. Roll and J. L. Geerties, "Unlocking value-based pricing: the moderating roles of pricing capabilities and contingency factors in B2B markets," Journal of Revenue and Pricing Management, vol. 24, pp. 232-253, 2025. doi: 10.1057/s41272-025-00530-z.

[7] C. H. Rashid, I. Shafi, J. Ahmad, et al., "Software Cost and Effort Estimation: Current Approaches and Future Trends," IEEE Access, vol. 11, pp. 99268-99288, 2023. doi: 10.1109/ACCESS.2023.3312716.

[8] R. R. Putri, D. Siahaan, and C. Fatichah, "A Comparative Study on COCOMO II Model for Cost Estimation," in Proc. 13th IEEE Int. Conf. ICCSCE, Penang, 2023, pp. 226-231. doi: 10.1109/ICCSCE58721.2023.10237162.

[9] M. Fernandez-Diego, E. R. Mendez, et al., "An Update on Effort Estimation in Agile Software Development: A Systematic Literature Review," IEEE Access, vol. 8, pp. 166768-166800, 2020. doi: 10.1109/ACCESS.2020.3021664.

[10] M. Fu and C. Tantithamthavorn, "GPT2SP: A Transformer-Based Agile Story Point Estimation Approach," IEEE Transactions on Software Engineering, vol. 49, no. 2, pp. 611-625, 2023. doi: 10.1109/TSE.2022.3158252.

[11] A. S. Cheemaa, M. Azhar, F. Arif, et al., "EGPT-SPE: story point effort estimation using improved GPT-2 by removing inefficient attention heads," Applied Intelligence, vol. 55, art. 994, 2025. doi: 10.1007/s10489-025-06824-4.

[12] Mizanur Rahman et al., "Review and Empirical Analysis of Machine Learning-Based Software Effort Estimation," IEEE Access, 2024. doi: 10.1109/ACCESS.2024.3404879.

[13] M. Awais et al., "A Comparative Analysis of Popular Software Effort Estimation Techniques," in Proc. IEEE Conf., 2023.

[14] M. Abadeer and M. Sabetzadeh, "Machine Learning-based Estimation of Story Points in Agile Development: Industrial Experience and Lessons Learned," in Proc. 2021 IEEE 29th Int. Requirements Engineering Conf. Workshops (REW), 2021, pp. 106-115. doi: 10.1109/REW53955.2021.00022.

[15] K. J. W. Arachchi and C. R. J. Amalraj, "An Agile Project Management Supporting Approach for Estimating Story Points in User Stories," in Proc. 2023 Int. Conf. ICITR, 2023. doi: 10.1109/ICITR61062.2023.10382930.

[16] M. M. I. Shamim, A. B. B. A. Hamid, T. E. Nyamasvisva, and N. S. B. Rafi, "Advancement of Artificial Intelligence in Cost Estimation for Project Management Success," Modelling, vol. 6, no. 2, art. 35, 2025. doi: 10.3390/modelling6020035.

[17] J. M. Lekraik and O. S. Ojekemi, "Advancing Digital Project Management Through AI: An Interpretable POA-LightGBM Framework for Cost Overrun Prediction," Systems, vol. 13, no. 12, art. 1047, 2025. doi: 10.3390/systems13121047.

[18] S. Salimimoghadam et al., "The Rise of Artificial Intelligence in Project Management: A Systematic Literature Review," Buildings, vol. 15, no. 7, art. 1130, 2025. doi: 10.3390/buildings15071130.

[19] E. Pereira, A. W. Graylin, and E. Brynjolfsson, "The Enterprise AI Playbook: Lessons from 51 Successful Deployments," Stanford Digital Economy Lab, Stanford Univ., Apr. 2026.

[20] S. Oesterle et al., "Investigating the Co-Creation of IT Consulting Service Value," Electronic Markets, vol. 32, no. 2, pp. 571-597, 2022. doi: 10.1007/s12525-020-00426-3.

[21] Minhui Hu, "Fixed-price or performance-based? Contract design with renegotiation for IT outsourcing," Journal of Management Science and Engineering, vol. 11, no. 1, 2026.

[22] J. Keranen, M. Kienzler, A. Salonen, H. Terho, and D. Totzek, "Gain-sharing in performance-based contracting," Industrial Marketing Management, vol. 115, pp. 1-13, 2023

Downloads

Published

2026-10-03

How to Cite

[1]
M. Shah, “Sizing AI-Driven Enterprise Engagements Under Uncertainty: A Probabilistic Scope and Pricing Framework for Pre-Sales Architects”, JAIC, vol. 10, no. 5, pp. 4297–4304, Oct. 2026.