Analisis Reschedule Keterlambatan Proyek Reparasi Dua Kapal dengan Metode Critical Path Method (CPM) dan Time Cost Trade Off (TCTO) pada KM. Kendhaga Nusantara 4 dan TB. Sorowako Star

  • Keisha Nandhini Syahada Universitas Diponegoro
  • Good Rindo Universitas Diponegoro
  • Ari Wibawa Budi Santosa Universitas Diponegoro
  • Naufal Abdurahman Prasetyo Universitas Diponegoro
Keywords: Repair, Time Cost Trade Off, Critical Path Method, Reschedule, Project Delay

Abstract

The rescheduling due to delays in the repair project of two ships being worked on simultaneously was carried out using the Critical Path Method (CPM) and Time Cost Trade Off (TCTO). The data obtained came from the repair lists of each ship. The aim was to expedite project completion and achieve the most optimal time and cost efficiency. Acceleration alternatives were calculated, such as adding labor and extending work hours on the critical path. The acceleration steps included adding 2 and 4 extra working hours and increasing the number of workers. The analysis results showed that the most optimal time reduction was achieved by adding 4 hours of overtime and 21 additional workers, successfully reducing the project duration from 55 days to 20 days, with a time efficiency of 64% and a cost savings from Rp 393,300,000 to Rp 390,330,000, a savings of Rp 2,970,000 or around 0.7%. The daily productivity for scrapping work reached a maximum of 650 m²/day, while the increase in labor and 2 extra working hours resulted in 780 m²/day, and 4 extra working hours resulted in 845 m²/day.

Downloads

Download data is not yet available.

References

M. Mustholiq,"Manajemen Perawatan Kapal," CV. Oxy Consultant, 2019.

M. Rivki, A. M. Bachtiar, “Teknologi Reparasi Kapal,” IKAPI, 2023.

J. Thoengsal, "Metode Optimalisasi Penjadwalan Pelaksanaan Proyek Konstruksi Menggunakan Metode Critical Path Method (CPM)," CV. Tohar Mulia, 2022.

M. F. K. Amrullah, U.Budiarto and A. F. Zakki, “Penjadwalan Proyek Reparasi Kapal Tugboat Selat Legundi II-206 Dengan Metode Time Cost Trade-Off (TCTO) dan Project Evaluation And Review Technique (PERT),” Jurnal Teknik Perkapalan, vol. 11, no. 1, 2023.

A. G. Mahardika, H. Fadriani, Muntiyono, S. Afiyah and G. D. Ramady, “Analysis of Time Acceleration Costs in Level Building Using Critical Path Method,” Institute of Physics, 2019.

L. A. Juniarta, Kustamar and S. Aziz, “Evaluation Of Construction Implementation On Warehouse Receipt Building Using Time Cost Trade-Off Analysis Method (Case Study of Warehouse Building Project at Tumpang, Indonesia),” ITN Malang, 2017.

M. F. Rasidi, G. Rindo, and S. Jokosisworo, “Analisa Percepatan Project (Project Crashing) Pada Perbaikan Kapal TB. Dermaga Mawar Kencana Menggunakan Critical Path Method (CPM) dan Project Evaluation and Review Technique (PERT),” Jurnal Teknik Perkapalan, 2024.

H. B. Ibrahim, "Rencana dan Estimate real of Cost," Bumi Aksara, 2001.

H. Rani, "Manajemen Proyek Konstruksi," Universitas Muhammadiyah 2016.

I. Soeharto, "Manajemen Proyek (Dari Konseptual Sampai Operasional)," IKAPI, 1999.

Presiden Republik Indonesia,"Perjanjian Kerja Waktu Tertentu, Alih Daya, Waktu Kerja, dan Waktu Istirahat, dan Pemutusan Hubungan Kerja.” Republik Indonesia, 2021.

Published
2024-10-22